What Is a Snagging Report?

A snagging report is a numbered list of every defect found in a new property before handover. Each entry shows the room, the exact spot, what is wrong and how serious it is, with a photo as proof.

In Dubai the report goes to the developer's handover or customer care team, who assign each item to a contractor. A clear report gets defects fixed; a vague one gets items closed without action.

The report is also your record. If something is not fixed, it shows the defect was raised before you accepted the property.

Who books it

New-home buyersBefore signing the handover and collecting the keys.
Overseas ownersWho need to see the condition of the unit without travelling.
InvestorsWho want defects fixed before the first tenant moves in.
Owners already handed overWho need a report to send within the defects liability period.
Zia engineer going through a snagging report with a new property owner in Dubai
When to Book

When You Need the Report

The report has the most power at specific points in the handover:

Before signing the handover

The developer is still keen to complete the handover, and you have not yet accepted the unit's condition.

Before the final payment, where it applies

Defects raised before you pay in full tend to be resolved faster.

Before furniture arrives

An empty unit shows every surface; furniture hides damage and makes repairs harder.

If you already have the keys

Send the report within the defects liability period so repairs are still the developer's cost.

Handover coming up?Book now and get your report in 24 hours — or 6–12 hours with express delivery.

How a Zia Snagging Report Is Organised

Every report follows the same structure, so you, your agent and the developer can find any item in seconds.

Summary page of a Zia snagging report showing snags by severity
Summary page
Room page of a snagging report with numbered defects and photos
Room section
Test results page of a snagging report with electrical and AC readings
Test results

Summary page

  • Property, unit and inspection date
  • Total snags by severity
  • Top items to raise first
  • Inspector name and credentials

Room sections

  • Rooms in walking order
  • Numbered snags with photos
  • Exact location in the room
  • Short, clear description

Test results

  • Socket, DB board and earth tests
  • Water pressure and drainage
  • AC temperatures per room
  • Thermal and moisture images

Sign-off

  • Items fixed at re-inspection
  • Items still open
  • Notes for your handover
  • PDF ready to share

What Each Entry Looks Like

These are typical examples of how items appear in a report (illustrative only):

#014 · Master bathroom · High

Grout gap and missing sealant where the shower tray meets the wall — water can reach the room behind.

#027 · Living room · Medium

Three hollow tiles near the balcony door, found by tap test — likely to crack under load.

#033 · Kitchen · Medium

Cabinet door misaligned and soft-close hinge not working.

#041 · Bedroom 2 · Low

Paint patch with uneven finish on the ceiling, visible in daylight.

#052 · Balcony · High

Floor falls toward the door instead of the drain; water pools at the threshold.

#060 · DB board · High

Earth-leakage protection did not trip within the test limit — electrician to check.

Close-up of a snag marked with tape during a snagging inspection in Dubai
How We Inspect

From Inspection to a Fixed Property

Inspection day

Our engineers inspect the unit against a 400+ point checklist and test the main systems.

Report delivered

Within 24 hours as standard, or 6–12 hours with express delivery.

Developer fixes

You send the report; the developer's team works through each numbered item.

Re-inspection

We return free of charge, check every item and update the report with what is closed and what is open.

Tools used on this inspection

Snagging app used for snagging reportSnagging app
Thermal imaging camera used for snagging reportThermal imaging camera
Moisture meter used for snagging reportMoisture meter
Hollow tile detector used for snagging reportHollow tile detector

How to Send the Report to Your Developer

Email the PDF to the developer's handover or customer care team and ask for a reference number and a target date for repairs. Keep every reply and every version of the list they send back.

Only close an item when you have seen the repair, not when you receive a message saying it is done. That is what the re-inspection is for.

  • Send before the handover appointment
  • Ask for a reference number
  • Request a written target date
  • Book the free re-inspection
  • Sign once key items are closed
Property owner emailing a snagging report PDF to the developer's handover team
Price & Timing

Snagging Report Price

The report is included with every snagging inspection — there is no separate fee for it. Apartment snagging starts from AED 999; villas and townhouses are quoted by size.

If your handover is close, choose express delivery and receive the report in 6–12 hours.

Apartment snagging + reportFrom AED 999
Villa / townhouseQuoted by size
Standard deliveryWithin 24 hours
Express delivery6–12 hours
Re-inspection after fixesFree
Dubai Rules

Your Rights at Handover

These rules explain why the report matters and how long the developer is responsible:

Inspection before handover

RERA Circular No. 2 of 2021 supports owners inspecting their property before handover.

One year for installations

Under Dubai Law No. 6 of 2019, developers must repair defective electrical, mechanical and sanitary installations for one year from handover.

Ten years for structure

The same law makes developers liable for structural defects for ten years from the completion certificate, and DLD retains 5% of project escrow for one year as a defects guarantee.

General information, not legal advice. Check your contract and the relevant authority for your case.

Our Engineers

Our Team at Work

Zia's engineers on snagging inspections across Dubai — the same team that will inspect your home and write your report.

Two Zia engineers arriving at a new Dubai apartment tower for a snagging inspection
On siteEngineers arriving for a handover inspection
Engineer tap-testing floor tiles for hollow spots during a snagging inspection in Dubai
Tap testTap-testing floor tiles for hollow spots
Engineer marking a wall defect with tape during a snagging inspection
Marking snagsMarking a defect with tape before photographing it
Engineer testing sockets and the distribution board in a new Dubai apartment
ElectricalTesting sockets and the DB board
Engineer logging a snag with a photo on a tablet for the snagging report
ReportingLogging each snag with a photo on the snagging app

Related Inspections

New-home snagging inspection at handover in Dubai

Property snagging inspection

Book the inspection that produces this report.

Electrical safety inspection of a distribution board in Dubai

Electrical test results

How socket and DB board findings are graded.

Commercial property inspection of an office in Dubai

Commercial handover report

Snagging an office or shop instead of a home.

Move-in condition report inspection in a Dubai apartment

Tenancy condition report

A similar report for tenants and landlords.

Zia Property Snagging lead engineer

Who inspects your property? Every snagging report is written and checked by Zia's RERA-approved engineers before it reaches you.

FAQ

Snagging Report FAQs

Straight answers to what people ask us about snagging reports in Dubai.

What is a snagging report?

It is a numbered list of every defect found in a new property before handover, with photos, exact locations and severity ratings. The developer uses it to fix the items before you accept the keys.

How long does it take to get the snagging report?

Standard delivery is within 24 hours of the inspection. Express delivery in 6–12 hours is available if your handover is close.

Can I send the report directly to my developer?

Yes. The PDF is designed to go to the developer's handover or customer care team as it is.

What if the developer refuses some items?

Ask for the refusal in writing with a reason. Our report gives the location, photo and severity for each item, which helps you follow up. For serious disputes, take technical or legal advice.

I already received my keys — is it too late?

No. Inspect as soon as possible and send the report within the defects liability period, so repairs remain the developer's responsibility.

Is the re-inspection included?

Yes. After the developer fixes the snags, we re-inspect free of charge and update the report to show what has been closed.

Book Now

Book Your Snagging Inspection

Share your property type, community and handover date. A certified engineer will call you back to confirm the date and a fixed written price.

Mon–Sat, 24 hours · Office 1606, Empire Heights A, Business Bay, Dubai

Thank you — your request has been received. We'll call you shortly.

We only use your details to contact you about this booking.

Call Now Button
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.